Commercial glazing questions, answered directly.

System selection, pricing structure, schedule, code compliance and maintenance — the questions that come up before a scope is released.

01

System selection

How do I know whether my project needs storefront or curtain wall?

Storefront sits within a single opening and is supported at the head and sill, typically one story. Curtain wall spans continuously past floor lines and hangs off the structure at each slab edge. If the glazed area crosses a floor line, it is curtain wall regardless of how the drawings label it.

Storefront systems

Should the curtain wall be unitized or stick-built?

Unitized is glazed in the shop and set as finished panels — faster on site, less weather exposure, best for repetitive elevations and occupied buildings. Stick-built is assembled at the building and is more economical on low-rise, ground-accessible or geometrically irregular elevations.

Curtain wall

What is the difference between European-style and American-style systems?

European-style framing uses narrow face widths, flush exterior planes and multi-chamber polyamide isolators, delivering slimmer sightlines and better condensation resistance. American-style framing uses wider profiles with captured glazing and snap-on stops, and matches most of the corridor's existing building stock at a lower cost.

Curtain wall systems

Do I need a thermally broken system?

In conditioned space, yes — an un-broken aluminum frame conducts heat straight through the wall, fails current energy code paths and produces winter condensation on interior frame faces. Non-thermal framing remains appropriate only in unconditioned areas such as parking structures.

Thermally broken storefront
02

Scope and pricing

How is a glazing scope priced?

By system type, opening quantity and size, glass makeup, finish, hardware schedule, and — on retrofit and remediation work — access. Rigging, lifts and sequencing frequently cost more than the materials, which is why an access-free scope description produces an unreliable number.

Request a proposal

Can I get a price without drawings?

A budget-level range, sometimes. A firm number needs enough information to size the scope: elevation area or opening count, existing system type, access method and schedule. Photos of the existing condition plus approximate dimensions are often enough to start.

Submit what you have

What drives the cost of sealant remediation?

Access, not linear footage. Swing-stage rigging, roof anchorage, permits and mobilization dominate the price, which is why an entire elevation is dramatically cheaper per foot than three separate spot-repair calls on the same building.

Weatherproofing & silicone

Do you quote all four systems on one project?

Yes. Storefront, curtain wall, entry doors with hardware, and perimeter weatherproofing are frequently one coordinated scope on a facade project, priced as separate line items so the owner can release them independently.

Request a multi-system proposal
03

Schedule and execution

What are typical lead times?

The controlling items are shop drawing approval and glass fabrication, both of which sit ahead of field work. Approval turnaround is usually the largest variable and is inside the owner's and architect's control, not the installer's.

Curtain wall lead time factors

Can this be done while the building stays occupied?

Yes, with sequencing designed for it — bay-per-night storefront replacement, floor-by-floor unitized setting, or elevation-by-elevation sealant work. The requirement is that the envelope is closed at the end of every shift, which favours shop-glazed assemblies.

Storefront replacement sequencing

Do you work on new construction, retrofit, or both?

Both. New construction work is coordinated against the specification and structural interface; retrofit work starts with a field survey because existing openings rarely match the original drawings after decades of building movement.

Describe your project stage
04

Doors, hardware and compliance

Can an existing entrance be brought into ADA compliance without replacing the doors?

Often yes. Most accessibility failures are hardware and adjustment issues — dragging pivots, oversized closer springs, non-compliant operating hardware — resolved with a low-energy operator and coordinated closer sizing rather than new leaves.

Entry doors & hardware

Our egress doors have added surface bolts for security. Is that a problem?

Yes. Egress doors serving occupied space must release in a single motion without a key, tool or special knowledge. The compliant way to secure them is electrified hardware — an electric strike or latch retraction tied to access control — not added bolts.

Panic hardware & access control

Can hardware be changed on a fire-rated door?

Only with listed components and prep that stays inside the tested assembly. A rated opening is a listed door, frame, hinge, closer and latch tested together, and any unlisted modification voids the rating for the whole assembly.

Fire-rated door scope
05

Performance and maintenance

Water is coming in near a window. Is the glass leaking?

Usually not. Water travels, so the interior stain rarely marks the entry point. The common sources are failed perimeter joints, blocked weep paths and gasket failure — isolated by sequential water testing from the bottom up.

Leak diagnosis & remediation

How often should facade sealant be replaced?

Correctly installed silicone typically lasts 15 to 20 years and urethane 7 to 12, with south and west elevations failing years before north. Plan a close inspection every two to three years and budget remediation by elevation rather than by building.

Sealant remediation

Our frames sweat every winter. Will new glass fix it?

No. Condensation on metal is a frame conductivity problem. Better glass raises the glass surface temperature and leaves the mullion cold, concentrating the sweating on the frame. The fix is a thermally broken system with adequate frame condensation resistance.

Thermal performance
06

Working with us

How do I start a project?

Submit a proposal request with whatever documentation exists — drawings, elevations, a specification section, a hardware schedule or photographs of the condition. Every submission is reviewed and answered with scope and next steps.

Request a proposal

What area do you cover?

Northern and central New Jersey — Bergen, Hudson, Essex, Union, Passaic, Middlesex, Monmouth and Ocean counties, plus eastern Somerset. We do not cover the western counties.

Tell us the site location

Who do you typically work with?

General contractors, architects, owners' representatives, building engineers and facility managers on commercial and institutional buildings. All work is scoped against drawings, a schedule and a specification.

Start a scope conversation

Deeper reference

Longer technical answers live in the guides.

Technical guides
Next step

Question not answered here?

Submit the project detail with your proposal request. Every submission is reviewed and answered with scope and next steps.